The opportunity
2/2 · Clear, recurring pain
Czech towns, hospitals and regions can wait months to sign a contract when a losing bidder asks the competition office to review the tender.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- Bidders asked for 268 reviews in 2025, up from 195 in 2024.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- A contract under review was blocked for 5 months on average.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- The office ordered 141 interim measures in 2025, such as bans on signing.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”Zdravotnický deníkzdravotnickydenik.czZdravotnický deník — signing ban on a hospital tender (another site)A May 2026 case: the competition office barred a regional hospital company from signing a 24M CZK furniture contract and sent a bidder's objections back to it.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
The opportunity
About this section
- What this shows
- The problem as it is today: what goes wrong, and who it costs.
- Why it matters to a builder
- Documented pain means you will not have to convince buyers the problem exists before you can sell them the fix.
- How to read the score
- 2/2 means clear, recurring pain: documented complaints, a petition or industry pressure. Scattered complaints make it 1/2.
Czech towns, hospitals and regions can wait months to sign a contract when a losing bidder asks the competition office to review the tender.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- Bidders asked for 268 reviews in 2025, up from 195 in 2024.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- A contract under review was blocked for 5 months on average.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- The office ordered 141 interim measures in 2025, such as bans on signing.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”Zdravotnický deníkzdravotnickydenik.czZdravotnický deník — signing ban on a hospital tender (another site)A May 2026 case: the competition office barred a regional hospital company from signing a 24M CZK furniture contract and sent a bidder's objections back to it.
The competition office reviews public tenders when a bidder complains, and its decisions can be appealed.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- With an appeal, the wait grows to 7 to 9 months, and 45% of disputes were appealed in 2022.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- Tenders under first review in 2022 were worth about 80bn CZK.VeKLEPodok.gov.czWithdrawn procurement-review bill — impact assessment (another site)The impact assessment of a 2024 government bill to speed up tender reviews, withdrawn before it passed: how many tenders are reviewed, their value and the cost of the wait.In the source’s words“Návrh zákona, kterým se mění zákon č. 134/2016 Sb. o zadávání veřejných zakázek, ve znění pozdějších předpisů, a některé další související zákony — Plán legislativních prací vlády na rok 2024”
- The ministry puts the cost of each extra day of waiting at about 6M CZK of public money.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- The office's head says many challenges come from badly prepared tenders and over-complicated conditions that invite bidders to attack them.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- The office says the buyer alone answers for lawful conditions, and any fault in them counts against the buyer.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- The office says it steps into at most 2–3% of tenders, mostly large ones.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
- Bidders lodged 205M CZK in deposits to file challenges in 2025, and 70M CZK of it went to the state.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
Suggested solution
Build a service that checks a town's or hospital's tender conditions against the competition office's past rulings before the tender goes out, and defends the buyer if a bidder complains, as similar services already do in Germany and the United States.
- The town or hospital. Today: Writes the tender conditions and runs the tender. With the suggested solution: Has the conditions checked before publishing.
- Who does this is not known. Today: Whether anyone checks the conditions first is not known. With the suggested solution: A checker compares them with past rulings.
- A losing bidder. Today: Asks the competition office for a review. With the suggested solution: Can still ask for a review.
- Competition office. Today: Can bar signing while it decides. With the suggested solution: Rules on fewer weak conditions.
- The town or hospital. Today: Waits for the decision, then any appeal. With the suggested solution: Has its defence ready from the start.
Not known: whether anyone checks the conditions first.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Suggested solution
About this section
- What this shows
- One way to solve the problem, and how the work would run with it.
- Why it matters to a builder
- It is a starting point to test with buyers, not a plan. The sections below are the evidence for and against it.
Build a service that checks a town's or hospital's tender conditions against the competition office's past rulings before the tender goes out, and defends the buyer if a bidder complains, as similar services already do in Germany and the United States.
A town or hospital writes its tender conditions, a losing bidder asks the competition office to review them, and the contract often waits months for the answer.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- The town or hospital. Today: Writes the tender conditions and runs the tender. With the suggested solution: Has the conditions checked before publishing.
- Who does this is not known. Today: Whether anyone checks the conditions first is not known. With the suggested solution: A checker compares them with past rulings.
- A losing bidder. Today: Asks the competition office for a review. With the suggested solution: Can still ask for a review.
- Competition office. Today: Can bar signing while it decides. With the suggested solution: Rules on fewer weak conditions.
- The town or hospital. Today: Waits for the decision, then any appeal. With the suggested solution: Has its defence ready from the start.
Not known: whether anyone checks the conditions first.
Why now
0/3 · No deadline
No new deadline forces buyers to act, but challenges rose by a third in 2025, and each one can freeze a contract for months.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- A hospital company was barred from signing a 24M CZK contract in May 2026.Zdravotnický deníkzdravotnickydenik.czZdravotnický deník — signing ban on a hospital tender (another site)A May 2026 case: the competition office barred a regional hospital company from signing a 24M CZK furniture contract and sent a bidder's objections back to it.
- Each extra day of review costs public budgets about 6M CZK.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- Court review after the office took about 550 days on average.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Why now
About this section
- What this shows
- The dated rules and events that push buyers to act, soonest first.
- Why it matters to a builder
- A dated rule turns “nice to have” into “must buy by”, and tells you how long the window stays open.
- How to read the score
- 3/3 means an enacted rule binds these buyers within 18 months and names a penalty. Without a named penalty it is 2/3. A draft law, a rule on someone else, or a date further out is 1/3.
No new deadline forces buyers to act, but challenges rose by a third in 2025, and each one can freeze a contract for months.2 sourcesuohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení…”mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- A hospital company was barred from signing a 24M CZK contract in May 2026.Zdravotnický deníkzdravotnickydenik.czZdravotnický deník — signing ban on a hospital tender (another site)A May 2026 case: the competition office barred a regional hospital company from signing a 24M CZK furniture contract and sent a bidder's objections back to it.
- Each extra day of review costs public budgets about 6M CZK.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
- Court review after the office took about 550 days on average.mmr.gov.czRegional development ministry — ten myths about review reform (another site)The ministry that writes the procurement law, on how long tenders under review are blocked and what each extra day costs public budgets.
The dates behind this:
- In June 2024 the regional development ministry drafted a bill to speed up reviews, and it was withdrawn before it passed.VeKLEPodok.gov.czWithdrawn procurement-review bill — impact assessment (another site)The impact assessment of a 2024 government bill to speed up tender reviews, withdrawn before it passed: how many tenders are reviewed, their value and the cost of the wait.In the source’s words“Návrh zákona, kterým se mění zákon č. 134/2016 Sb. o zadávání veřejných zakázek, ve znění pozdějších předpisů, a některé další související zákony — Plán legislativních prací vlády na rok 2024”
- The review numbers rose from 195 in 2024 to 268 in 2025.uohs.czCompetition office — annual report 2025 (another site)The competition office's own yearly report: how many tender reviews bidders asked for, how many signing bans it ordered, and what its head says causes the disputes.In the source’s words“V mnoha případech je na vině nekvalitní příprava zadávacích řízení, kdy zejména nedostatečně zpracované projekty nebo překombinované nastavení zadávacích podmínek přímo vyzývají k tomu, aby je dodavatelé napadali.”
Willing to pay
2/2 · Clear signs
Yes, towns already pay law firms and tender administrators to write tender documents and to defend tenders at the office.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Towns pay law firms monthly for work on one tender's documents.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Towns sign one-off contracts to be represented in a single review.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Small firms publish fixed prices per tender and per objection.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Per case
Per project
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Willing to pay
About this section
- What this shows
- Who already spends money on this problem, how much, and how they buy.
- Why it matters to a builder
- If people already pay for this, even by hand or through a consultant, you are replacing a spend, not creating a budget.
- How to read the score
- 2/2 means a Czech buyer has paid for this, or a priced job also gets public money that pays part of it. A price on file makes it 1/2. Public money alone earns nothing. Only public buyers publish what they pay, so problems sold to private firms often score lower.
Yes, towns already pay law firms and tender administrators to write tender documents and to defend tenders at the office.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Towns pay law firms monthly for work on one tender's documents.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Towns sign one-off contracts to be represented in a single review.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Small firms publish fixed prices per tender and per objection.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
What one town paid to defend a tender, and another for its tender documents, is under Willing to pay.
Per case
Per project
What one buyer pays
- 30 000 CZK per project
- Czech public buyers outsourcing one tender petrjakubicek.czPetronium — tender administration price list (another site)A Czech firm's published price for running a whole tender for a public buyer, with separate prices for objections and filings at the competition office.
- 51 410 CZK per case
- Černošice (town) cityvizor.czČernošice — legal work on tender documents (another site)What a Czech town paid a law firm in one month for legal work on the tender documents and the tender for a housing project.
- 63 000 CZK per case
- Žďár nad Sázavou (town) Registr smluvsmlouvy.gov.czŽďár nad Sázavou — defending one tender at the office (another site)What a Czech town agreed to pay a law firm to represent it before the competition office in a review of one of its tenders.
Validated abroad
3/3 · Proven in 2+ markets
In Germany and the United States, established firms prepare and check public buyers' tender documents, by hand and in software.2 sourcesausschreibungen.staatsanzeiger.deStaatsanzeiger für Baden-Württemberg (another site)A German publisher that prepares and checks tender documents for public buyers and runs their tenders, with hundreds of public buying offices as customers.statescoop.comOpenGov (another site)American procurement software that builds tender documents from templates carrying each agency's own rules, used by about 1,900 agencies and cities.
- Staatsanzeiger für Baden-Württemberg (another site)Based in Germany
- OpenGov (another site)Based in United States
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Validated abroad
About this section
- What this shows
- Companies abroad that already sell a solution, and how far along they are.
- Why it matters to a builder
- Established companies selling it in other markets show that buyers will pay, so you are not betting on an untested idea.
- How to read the score
- 3/3 means established in two or more markets, one of them near Czechia. 2/3 is one established company, 1/3 only early players.
In Germany and the United States, established firms prepare and check public buyers' tender documents, by hand and in software.2 sourcesausschreibungen.staatsanzeiger.deStaatsanzeiger für Baden-Württemberg (another site)A German publisher that prepares and checks tender documents for public buyers and runs their tenders, with hundreds of public buying offices as customers.statescoop.comOpenGov (another site)American procurement software that builds tender documents from templates carrying each agency's own rules, used by about 1,900 agencies and cities.
- ausschreibungen.staatsanzeiger.deStaatsanzeiger für Baden-Württemberg (another site)A German publisher that prepares and checks tender documents for public buyers and runs their tenders, with hundreds of public buying offices as customers.
A Stuttgart publisher that prepares and checks tender documents for public buyers and runs their tenders; it says it has supported public buyers for over 30 years, counts 634 public buying offices and 420 accompanied tenders, and names customers such as the towns of Fellbach, Winnenden and Leonberg (own site, 2026).
- statescoop.comOpenGov (another site)American procurement software that builds tender documents from templates carrying each agency's own rules, used by about 1,900 agencies and cities.
Procurement software that builds compliant tender documents from templates that carry an agency's own policies; about 1,900 state agencies and cities as customers when Cox Enterprises took majority ownership at a $1.8B valuation in February 2024 (StateScoop, 2024).
In Germany, a publisher has helped public buyers run tenders for over 30 years and counts 634 public buying offices as users.ausschreibungen.staatsanzeiger.deStaatsanzeiger für Baden-Württemberg (another site)A German publisher that prepares and checks tender documents for public buyers and runs their tenders, with hundreds of public buying offices as customers. In the United States, software that builds tender documents to each agency's own rules serves about 1,900 agencies and cities.statescoop.comOpenGov (another site)American procurement software that builds tender documents from templates carrying each agency's own rules, used by about 1,900 agencies and cities. See Validated abroad.
Market gap
0/2 · Crowded
Established Czech tender administrators and law firms already write tender conditions for public buyers and defend them, by hand.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
New, selling this: QCM Administrace (since 2010), Petronium (since 2012), Urban legal (since 2023). Established, selling this: RTS (since 1998), HAVEL & PARTNERS (since 2001), Compet Consult (since 2002). New, selling something nearby: TENDERIX. Established, selling something nearby: Equica (since 2001), QCM (E-ZAK) (since 2001), Tender systems (Tender arena) (since 2012).
- EarlySells this · since 2010QCM Administrace (another site)Prepares tender conditions, runs tenders for public buyers and says it argues their case before the competition office.Sources and the full note are in Read more.
- EarlySells this · since 2012Petronium (another site)A small firm with a public price list for running a whole tender for a buyer, handling objections and filing at the competition office.Sources and the full note are in Read more.
- EarlySells this · since 2023Urban legal (another site)A Brno law firm that represents towns before the competition office: Žďár nad Sázavou signed it in April 2025 to defend one tender (contract register).Sources and the full note are in Read more.
- EstablishedSells this · since 1998RTS (another site)Runs public tenders for towns from the notice to contract changes.Sources and the full note are in Read more.
- EstablishedSells this · since 2001HAVEL & PARTNERS (another site)A law firm that writes tender documents for public buyers and represents them in disputes.Sources and the full note are in Read more.
- EstablishedSells this · since 2002Compet Consult (another site)Runs public tenders for towns and hospitals, including setting their conditions.Sources and the full note are in Read more.
- EarlySells something nearbyTENDERIX (another site)Sells an AI assistant that answers questions about the competition office's decisions and the courts' case law.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2001Equica (another site)A consultancy that sells towns data-protection and IT services and offers an AI tool that drafts tender documents from earlier published tenders.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2001QCM (E-ZAK) (another site)Sells E-ZAK, the certified online tool many public buyers run their tenders in.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2012Tender systems (Tender arena) (another site)Sells Tender arena, a certified online tender tool used by over 3,700 tendering bodies, by its own count.Sources and the full note are in Read more.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Market gap
About this section
- What this shows
- Czech companies that already sell this, and firms nearby that sell something else.
- Why it matters to a builder
- A mature Czech seller means taking customers from an incumbent. Firms nearby still matter: the buyer may already pay them.
- How to read the score
- More points mean a more open field. 2/2 means no Czech company sells this, 1/2 only early ones do, 0/2 a mature one does.
Established Czech tender administrators and law firms already write tender conditions for public buyers and defend them, by hand.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
New, selling this: QCM Administrace (since 2010), Petronium (since 2012), Urban legal (since 2023). Established, selling this: RTS (since 1998), HAVEL & PARTNERS (since 2001), Compet Consult (since 2002). New, selling something nearby: TENDERIX. Established, selling something nearby: Equica (since 2001), QCM (E-ZAK) (since 2001), Tender systems (Tender arena) (since 2012).
- EarlySells this · since 2010QCM Administrace (another site)Prepares tender conditions, runs tenders for public buyers and says it argues their case before the competition office.Sources and the full note are in Read more.
- EarlySells this · since 2012Petronium (another site)A small firm with a public price list for running a whole tender for a buyer, handling objections and filing at the competition office.Sources and the full note are in Read more.
- EarlySells this · since 2023Urban legal (another site)A Brno law firm that represents towns before the competition office: Žďár nad Sázavou signed it in April 2025 to defend one tender (contract register).Sources and the full note are in Read more.
- EstablishedSells this · since 1998RTS (another site)Runs public tenders for towns from the notice to contract changes.Sources and the full note are in Read more.
- EstablishedSells this · since 2001HAVEL & PARTNERS (another site)A law firm that writes tender documents for public buyers and represents them in disputes.Sources and the full note are in Read more.
- EstablishedSells this · since 2002Compet Consult (another site)Runs public tenders for towns and hospitals, including setting their conditions.Sources and the full note are in Read more.
- EarlySells something nearbyTENDERIX (another site)Sells an AI assistant that answers questions about the competition office's decisions and the courts' case law.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2001Equica (another site)A consultancy that sells towns data-protection and IT services and offers an AI tool that drafts tender documents from earlier published tenders.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2001QCM (E-ZAK) (another site)Sells E-ZAK, the certified online tool many public buyers run their tenders in.Sources and the full note are in Read more.
- EstablishedSells something nearby · since 2012Tender systems (Tender arena) (another site)Sells Tender arena, a certified online tender tool used by over 3,700 tendering bodies, by its own count.Sources and the full note are in Read more.
Sells this 6
- Established: HAVEL & PARTNERS (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
A law firm that writes tender documents for public buyers and represents them in disputes. Established: registered 2001 (ARES), with named public customers paying it in 2025–2026 for this work: Černošice for the tender documents of a housing project and the Karlovy Vary region as tender administrator (CityVizor).
Found by the register’s market check
- Established: Compet Consult (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Runs public tenders for towns and hospitals, including setting their conditions. Established: registered 2002 (ARES), with named customers on its own reference list, such as Krajská nemocnice Liberec, Nemocnice Jablonec nad Nisou and the town of Frýdlant.
- Established: RTS (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Runs public tenders for towns from the notice to contract changes. Established: registered 1998 (ARES), with named customers paying it in 2025–2026: Moravská Třebová, Kroměříž, Uherský Brod and Ostrava (CityVizor).
Found by the register’s market check
- Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Prepares tender conditions, runs tenders for public buyers and says it argues their case before the competition office. Registered 2010 (ARES); its service page names no customer, so no limb of the established test is shown for this company on its own.
Found by the register’s market check
- Early: Urban legal (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
A Brno law firm that represents towns before the competition office: Žďár nad Sázavou signed it in April 2025 to defend one tender (contract register). Registered February 2023 (ARES); one public customer verified, so the test is not passed.
Found by the register’s market check
- Early: Petronium (another site)petrjakubicek.czPetronium — tender administration price list (another site)A Czech firm's published price for running a whole tender for a public buyer, with separate prices for objections and filings at the competition office.
A small firm with a public price list for running a whole tender for a buyer, handling objections and filing at the competition office. Registered 2012 (ARES); nobody it has worked for could be found.
Sells something nearby 4
- Established: QCM (E-ZAK) (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Sells E-ZAK, the certified online tool many public buyers run their tenders in. The tool carries a tender through its steps; it does not judge whether the conditions will hold up. Registered 2001 (ARES), paid by many public bodies in CityVizor.
Found by the register’s market check
- Established: Tender systems (Tender arena) (another site)3 sourcesRegistr smluvsmlouvy.gov.czŽďár nad Sázavou — defending one tender at the office (another site)What a Czech town agreed to pay a law firm to represent it before the competition office in a review of one of its tenders.cityvizor.czČernošice — legal work on tender documents (another site)What a Czech town paid a law firm in one month for legal work on the tender documents and the tender for a housing project.petrjakubicek.czPetronium — tender administration price list (another site)A Czech firm's published price for running a whole tender for a public buyer, with separate prices for objections and filings at the competition office.
Sells Tender arena, a certified online tender tool used by over 3,700 tendering bodies, by its own count. It publishes documents and takes bids; it does not check the conditions for legal risk. Registered 2012 (ARES).
- Established: Equica (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
A consultancy that sells towns data-protection and IT services and offers an AI tool that drafts tender documents from earlier published tenders. It drafts; it does not check conditions against the office's rulings. Registered 2001 (ARES), with named customers: the towns of Kroměříž and Bystřice paid it in 2025 (CityVizor).
Found by the register’s market check
- Early: TENDERIX (another site)Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
Sells an AI assistant that answers questions about the competition office's decisions and the courts' case law. It is a research tool, not a check of a buyer's own documents. The company was registered in January 2026 (ARES); no customer count was found.
Found by the register’s market check
In the room, sells nothing 2
- No source on file
The regional development ministry writes the procurement law and in June 2026 began testing a state AI tool that flags risks in the conditions of small contracts, the kind the competition office does not review. A free state tool is what many buyers may try first.
- No source on file
The competition office reviews public tenders when a bidder complains, can bar the buyer from signing meanwhile, and publishes its decisions. It sells nothing; it is the body every set of conditions has to satisfy.
- Firms registered as far back as 1998 run tenders for towns and hospitals.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- Law firms represent towns before the competition office, case by case.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
- A free state AI check covers only small contracts the office never reviews.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand.
No Czech product was found that checks a tender's conditions against the office's past decisions before it is published.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand. Young AI tools answer questions about those decisions or draft documents from earlier tenders.Market checkcompetconsult.czCzech check — who checks and defends tender conditions (another site)Czech-language search, the state business register, the contract register and towns' published invoice books: established Czech firms already write tender conditions for public buyers and defend them, by hand. The rows are under Market gap.
Execution difficulty
1/3 · Hard
Makes it easier
- Towns and hospitals already pay outside firms for tender documents and for defence at the competition office.
- No licence is needed.
- The office publishes its decisions.
Makes it harder
- The buyers are public bodies that buy through tenders.
- Established Czech firms already serve many of them.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Execution difficulty
About this section
- What this shows
- What stands between you and the first sale: who buys, what permission selling needs, what it must plug into, and whether it needs outside money.
- Why it matters to a builder
- It tells you whether a small team can start selling soon, or needs a licence, a certification or funding first.
- How to read the score
- More points mean easier to enter: 3/3 is easy, 0/3 very hard. It is not added to the Opportunity total, and local competition does not count here: that is Market gap.
Hard
Makes it easier
- Towns and hospitals already pay outside firms for tender documents and for defence at the competition office.
- No licence is needed.
- The office publishes its decisions.
Makes it harder
- The buyers are public bodies that buy through tenders.
- Established Czech firms already serve many of them.
Local competition does not change this level. It is covered under Market gap.
Suggested first moves
- Build a list of the tender conditions the competition office most often strikes down, from its own published decisions.
- Ask the procurement heads of a few hospitals and mid-sized towns which of their tenders were challenged lately, and how long each contract waited.
- Offer a fixed-price second look at a tender's conditions before it is published.
P-0052 · Czech towns and hospitals can wait 5 months to sign a contract when a losing bidder complains
Suggested first moves
About this section
- What this shows
- A few concrete steps to start with.
- Why it matters to a builder
- They are cheap ways to learn whether buyers will pay, before you build much.
- Build a list of the tender conditions the competition office most often strikes down, from its own published decisions. The office's head names over-complicated conditions as a common cause, as The opportunity shows, so start with the conditions his office keeps overturning.
- Ask the procurement heads of a few hospitals and mid-sized towns which of their tenders were challenged lately, and how long each contract waited. Their answers tell you which kinds of tenders to check first and what a month of delay means to them.
- Offer a fixed-price second look at a tender's conditions before it is published. Sell it to buyers who write their own tenders, and to the firms under Market gap as a second pair of eyes on their work.
- Follow every new review request and signing ban the office publishes, and tell the affected buyer what similar cases decided. A buyer already caught in a review needs its defence fast, as Why now shows.